Learning Goal: Compare different production systems and select appropriate ones based on order and product.
Common systems:
- Make‑Through (Whole‑Garment): One operator sews the entire garment. Used in sample rooms or for very small orders. High skill needed, low output.
- Progressive Bundle System (PBS): The most common system. Bundles of cut pieces move from one operation to the next, each operator specialising in one or a few tasks. High efficiency but can create work‑in‑process (WIP) accumulation.
- Unit Production System (UPS): An overhead transporter automatically moves individual pieces to workstations. Reduces WIP and handling, but requires investment.
- Modular / Team Sewing: A small team of multi
skilled operators works together to complete a garment. Improves flexibility and quality, suited for quick style changes.
- Straight‑Line / One‑Piece Flow: Each piece moves instantly to the next operation, minimal WIP. Requires highly balanced lines and quick operators.
Choosing a system depends on order quantity, product complexity, skill level, and delivery urgency.
Step‑by‑step Explanation:
- For a 20,000‑unit basic t‑shirt order, Progressive Bundle System with high specialisation is most efficient.
- For a 50‑piece designer dress with intricate details, Make‑Through or Modular may be better.
- A factory with high mix/low volume may invest in UPS to reduce bundle handling.
- Evaluate lead time, space, and capital before changing a system.
Best Practices: Even in PBS, keep bundle sizes small (10–15 pieces) to reduce WIP and improve tracking.
Common Mistakes: Using PBS for very small runs—operators spend too much time handling bundles, not sewing.
Real Industry Example: A fast‑fashion supplier uses a hybrid: PBS for core operations, but a modular team for special finishes, boosting both speed and flexibility.
Mini Case Study: A factory switched from PBS to modular for a complex ladies’ blouse and reduced throughput time by 30% because multi‑skilled operators adjusted quickly to different tasks, eliminating waiting time.
Practical Activity: Draw a simple diagram of a Progressive Bundle System for a shirt line and label the typical operation sequence.
Assignment: Write a one‑page comparison of PBS and Modular systems, recommending a system for a childrenswear factory with frequent style changes (200–500 units per style).
Lesson Summary: The production system shapes efficiency and flexibility; choose the one that aligns with your order profile and workforce capability.
Key Takeaways:
- PBS is standard for large runs.
- Modular and Make‑Through for smaller, complex orders.
- UPS reduces handling but requires investment.