Learning Goal: Identify and interpret the KPIs that measure factory efficiency, quality, and delivery.
KPIs turn factory floor activity into actionable data. Common production KPIs include:
- Efficiency % = (Earned Standard Minutes / Minutes Worked) × 100. Measures how well operators achieve standard times.
- Productivity = Output / Input (e.g., pieces per operator per hour).
- On‑time Delivery % = Orders shipped on or before the deadline.
- Defect Rate (DHU) = Defects per Hundred Units. Often broken down by major and minor.
- WIP Level (Work‑in‑Process): Number of units on the floor unfinished. High WIP indicates imbalances.
- Absenteeism & Turnover – affects planning.
Definitions:
- Earned Standard Minutes – the total SMV of good garments produced.
- WIP – semi‑finished garments between operations.
Step‑by‑step Explanation:
- Collect daily output and attendance data.
- Calculate efficiency: if line produced 1000 mins of SMV and operators worked 1200 mins, efficiency = (1000/1200) × 100 = 83.3%.
- Track defect rate per line daily; plot on a chart.
- Monitor WIP visually or with data; target minimal WIP.
Best Practices: Display daily efficiency and quality dashboards on the factory floor to create visibility and motivation.
Common Mistakes: Ignoring absenteeism until it derails the schedule. Proactive attendance management is key.
Real Industry Example: A sportswear factory calculates hourly efficiency and adjusts operator allocation mid‑shift if a line falls behind.
Mini Case Study: A factory’s on‑time delivery was 95% but efficiency was low; they were meeting deadlines by overtime, eroding profit. Now they monitor both together.
Practical Activity: Using a sample data set (provided), calculate line efficiency and DHU for a sewing line over one week.
Assignment: Design a one‑page KPI dashboard for a factory manager, selecting the top six metrics and explaining why each matters.
Lesson Summary: KPIs provide the real picture; production management is impossible without measurement.
Key Takeaways:
- Efficiency, quality, delivery – the golden triangle.
- Low WIP = smooth flow.
- Visual dashboards drive improvement.